Title:


Evaluating The Scheduling of The Development Projects of Rural Electricity Network Distribution Using Critical Path Method


Author:


Mail Diqbal Satyanegara(1*)
Mail Widya Nur Bhakti Pertiwi(2)

(1) Fakultas Ekonomi dan BIsnis Universitas Sultan Ageng Tirtayasa, Indonesia
(2) Fakultas Ekonomi dan BIsnis Universitas Sultan Ageng Tirtayasa, Indonesia
(*) Corresponding Author
10.31002/rn.v5i2.4174| Abstract views : 0 | PDF views : 0

Abstract


Delay in the completion of a project is a problem that is often faced, it certainly has an impact on the entire project. CPM is one of the control tools to get a working picture of the project. In 2015, PT PLN South Banten Area made a Development Project of Rural Electricity Network Distribution in Banten. This project is held by an electrical installation services company, PT. Z, in June 2015.This project is due 150 days, PT. Z had defined time completion on 143 days, but the completion took 154 days. The type of research used in this research is quantitative research with analytical technique CPM approach. This research identified the least project schedule planning. There are three activities in this project schedule which are unlisted yet, therefore it affected the timeline of the project. Based on the CPM calculation, PT. Z could have shorten the work time down to 3 days with the cost of Rp 1.802.386.000

Keywords


Scheduling; Project; CPM

Full Text:

PDF

References


Angelin, A., & Ariyanti, S. (2019). Analisis Penjadwalan Proyek New Product Development Menggunakan Metode Pert Dan Cpm. Jurnal Ilmiah Teknik Industri, 6(1), 63–70. https://doi.org/10.24912/jitiuntar.v6i1.3025

Astari, N. M., Subagyo, A. M., & Kusnadi. (2021). Perencanaan Manajemen Proyek dengan Metode Critical Path Method (CPM) dan Program Evaluation and Review Technique (PERT). Jurnal Konstruksia, 13(1), 164–180. Retrieved from https://jurnal.umj.ac.id/index.php/konstruksia/article/view/9996

Heizer, Jay dan Render, B. (2011). Operation Management, 10th Edition. Boston: Pearson Education.

Hersanto. (2011). Manajemen Proyek. Dinas Pendidikan Provinsi Banten.

Husen, Abrar. (2011). Manajemen Proyek. Yogyakarta: Andi Offset.

Purhariani, Y., Riani, L.P., Meilina, R. (2017). Penerapan CPM dalam Pembangunan Rumah (Studi Kasus Pembangunan Rumah Tipe 36 Ukuran 6 m x 6 m di Jalan Balowerti Nomer 37 Kota Kediri). Simki-Economic. 01, 1-13.

Santosa, Budi (2003). Manajemen Proyek. Surabaya: Guna Widya

Soeharto, Iman. (1999). Manajemen Proyek (Dari Konseptual Sampai Operasional. Jakarta: Erlangga.

Sugiyono. (2009). Metode Penelitian Bisnis. Bandung: Pusat Bahasa Depdiknas.

Widiasanti, Irika dan Lenggogeni. (2013). Manajemen Konstruksi. Bandung: PT Remaja Rosdakarya.

Yulianto, A. (2013). Optimasi Penjadwalan Proyek Menggunakan CPM dengan Algoritma Genetika pada Studi Kasus Proyek Pembangunan Laboratorium Ekonomi Surabaya. Extrapolasi Jurnal Teknik Sipil Untag Surabaya. 06, 35-42.




DOI: https://doi.org/10.31002/rn.v5i2.4174

Article Metrics

Abstract view : 0 times
PDF - 0 times

Cited By

Refbacks

  • There are currently no refbacks.


Copyright (c) 2022 Jurnal REKOMEN (Riset Ekonomi Manajemen)

Creative Commons License
This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.

 
   
 Jurusan Manajemen Fakultas Ekonomi Universitas Tidar

Creative Commons License
Jurnal REKOMEN (Riset Ekonomi Manajemen) is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.